Trenchless Methods Compared: HDD, Thrust Boring, Pipe Jacking and Microtunneling

Trenchless construction covers several different methods. They are often grouped together, but each one works differently and suits different ground, length and pipe size. This article explains the main methods used in Saudi Arabia and how they differ.

Horizontal Directional Drilling (HDD)

HDD drills a steerable pilot bore along a planned path from the surface, enlarges it by reaming, then pulls the pipe or conduit back through the hole. A downhole tracking system guides the drill head. HDD suits long crossings of roads, rivers, wadis and shore approaches, and is used for steel pipelines, HDPE pipes and cable ducts. See our HDD page and Offshore & Shore Approach HDD page.

Thrust boring

Thrust boring is a separate method, not a type of HDD. A steel casing is pushed through the ground from a launch pit with hydraulic rams while the soil is removed. It is used for short crossings, for example under roads, in stable ground.

Pipe jacking and microtunneling

Pipe jacking pushes prefabricated pipe sections from a launch shaft to a reception shaft using hydraulic jacks. Microtunneling is a remotely controlled form of pipe jacking that uses a microtunnel boring machine (MTBM) and gives high accuracy in difficult ground. Both are suited to larger diameters and gravity lines. See our Microtunneling page.

Pipe ramming

Pipe ramming drives an open-ended steel casing through the ground with a percussive hammer. It is used for short crossings and carries a risk of ground disturbance, so ground conditions must be assessed first.

HDD techniques

Intersect drilling uses two rigs drilling from opposite ends to meet at a set point. Steering and tracking systems such as wireline and gyro guide the drill head along the design path. Offshore and shore approach HDD installs pipes and cables beneath the seabed from land to sea.

Choosing the right method

The right method depends on crossing length, pipe diameter, ground conditions, depth, access and environmental limits. These factors are assessed at the tender and design stage. LIFCON can advise on method selection for your project; please use our contact page.